Completed · 2024
Guard Pond Rectification Work
HDPE Lining Rectification
Duration
1 Month
Project Value
RM 143,000.00

Project Details
Parties, Delivery Structure & Scope
Project parties, delivery structure, and scope of work.
Project Owner
Petronas Chemicals Fertilizer Kedah
Client
Petronas
Main Contractor
Not Specified
Nominated Sub-Contractor
Directed Awarded
Scope of Work
HDPE Lining Rectification
HDPE Lining Rectification Works.
More Work